All the quartz stone is dyed and matched to the design specifications at the factory where it will be package and shipped for installation.

1. Step
Our patented resin is delivered to the job site.

2. Step
Quartz stones are packaged in paper and shipped to site. The colored stones are then mixed to specs on-site.

3. Step
After the stones are mixed to match color they are then loaded into the mixer.

4. Step
The mixer combines the perfect amount of resin with rocks ready to be spread on the floor.

5. Step
The workers then begin to spread the mixture on the floor by hand.

6. Step
The workers then trowel the stone to the desired 3/8″ thickness.

7. Step
Continuing to hand trowel the system gets the floor ready for the final hover trowel.

8. Step
The hover trowel closes and tightens the StoneCarpet® system to complete the installation process.

9. Step
After only 12 hours the floor is ready to walk on, 7 days later the floor reaches its optimal hardness.